This page was exported from Testking Free Dumps [ http://blog.testkingfree.com ] Export date:Thu Jan 16 18:50:30 2025 / +0000 GMT ___________________________________________________ Title: 2022 Realistic TestKingFree C_TS422_2020 Dumps PDF - 100% Passing Guarantee [Q22-Q43] --------------------------------------------------- 2022 Realistic TestKingFree C_TS422_2020 Dumps PDF - 100% Passing Guarantee Free SAP C_TS422_2020 Exam Questions and Answer NO.22 What does it mean for the production planner when MRP works with infinite capacities?  MRP assigns capacity requirements automatically to work center is with the earliest available capacity.  MRP creates capacity requirements without checking the capacity of a work center.  MRP creates capacity requirements only if the work center has sufficient capacity.  MRP assigns capacity requirements automatically after the last scheduled order on a work center. NO.23 When a developer creates a new SAP Fiori app, they begin by selecting a template to ensure the application has a consistent look-and-feel. What types of templates can a developer choose? There are 3 correct answers to this question.  Transactional  Factsheet  Web Dynpro  Analytical  Maintenance view NO.24 Mode selection is one of the scheduling options available in Advanced Planning in SAP S/4HANA. When can you use mode selection?  When multiple planned orders exists in one resource  When alternate resourcesare used within one operation  When multiple production versions are maintained for one product  When multiple operations are maintained for one product NO.25 What are the key aspects of SAP S/4HANA? There are 2 correct answers to this question.  SAP S/4HANA increases the data footprint.  SAP S/4HANA can be deployed on-premise, in the cloud, or a combination of both.  SAP S/4HANA has minor changes on data model.  SAP S/4HANA is built on SAP HANA NO.26 What do you use to schedule operations from planned orders so that the production plan can be fulfilled?  Demand Planning (DP)  Material Requirements Planning (MRP)  Capacity Requirements Planning (CRP)  Supply Network Planning (SNP) NO.27 For which planning-relevant data objects do you set just one indicator to include then in PP/DS?There are 2 correct answers to this question.  Plant  Material  Work center  Production version NO.28 Before a user can add multiple production versions in a material master, what information should be collected?There are 3 correct answers to this question.  Validity dates  Lot sizes  BOM status  Work center hierarchy  Task list group number NO.29 What is a work center hierarchy in SAP S/4HANA capacity planning?  A group of alternative work centers for production, structured in hierarchy levels by prior ties  A group of work centers in a parallel sequence that is used to split product on quantities and work on them in parallel  A group of work centers in a production line beingused in sequence for production  A group of alternative work centers providing a cumulative available capacity for production NO.30 Which material master data can you copy when you use the Copy Material program (transaction MMCC, Material Master Copier) to create new materials? There are 2 correct answers to this question.  Warehouse number data  MRP area data  Production version data  Storage location data NO.31 Which of the following is a valid sequence of the main activities in product on order processing?  Creation, scheduling, release, variance calculation, confirmation  Creation, release, scheduling, material withdrawal, confirmation  Creation, scheduling, release, material withdrawal, confirmation  Creation, staging, release, material withdrawal, confirmation NO.32 At the end of the MRP run you receive the exception message “Reschedule In Operation”. What caused the message to be generated?  The requirements date occurs that of a firmed planned receipt  The requirements date occurs before that of a firmed planned receipt  The requirement no longer exists  A firmed planned receipt cannot be rescheduled NO.33 Which technological advances enabled the development of SAP S/4HANA as the digital core?There are 3 correct answers to this question.  Multi core processors enabling parallelism of tasks  Capability to add to server landscape and scale  Wide adoption of web standards such as Service oriented architecture  Big and affordable memory  Advances in the three-tier architecture approach NO.34 A material has been set up as a phantomassembly by entering the special procurement key in the material master. How can you switch off the phantom assembly in a specific bill of material(BOM)?  Change the item category of the phantom assembly in the BOM.  Change the explosion type of the phantom assembly in the BOM.  Change the phantom item indicator for the phantom assembly in the BOM.  Change the special procurement key of the phantom assembly in the BOM. NO.35 Which options do you have to plan both quant ties and capacities during line loading in repetitive manufacturing? Note: There are 2 correct answers to this question.  Run MRP with automatic selection of production version.  Run PP/DS heuristics for repetitive manufacturing.  Run MRP with quotaarrangement.  Assign planned orders manual lying the planning table. NO.36 Which of the following is an advantage of MRP Live and NOT available in classical MRP? There are 2 correct answers to this question.  MRP Live can priorities demand from sales orders  MRP Live can propose alternative solutions  MRP Live can create production orders automatically  MRP Live can plan materials with recursive BOMs NO.37 The production plan is being disrupted by last minute demands that are entered in the system. Which is the most efficient way to handle last minute demands and protect the current production plan? There are 2 correct answers to this question.  In the material master record, set MRP type to PI and a planning time fence on the replenishment lead time of the material  Manually firm all planned orders for materials within the replenishment lead time of the material  In the material master record, set MRP type to P4 and a planning time fence on the replenishment lead time of the material  In the stock requirements list, set a manual firming fence for a date based on the replenishment lead time of the material NO.38 Which reports can you access via the order and resource reporting transaction in advanced planning? There are 3 correct answers to this question  Production list  WIP list  Production overview  Operation list  Planning file entries NO.39 Why would you use phantom assemblies? Note: There are 3 correct answers to this question.  To make the assignment of components easier  Tosimplify the structure of bills of material  To reduce the number of changes required in bills of material  To increase the number of planning levels  To reduce the number of material masters NO.40 What must be used in the system to plan the requirements for different subcontractors separately?  Planning plant  Storage locations  MRP areas  Production versions NO.41 You want to triggering-houseproduction of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?  Make-to-order production (20)  Planning without final assembly (50)  Planning with final assembly (40)  Planning at assembly level (70) NO.42 What are the consequences when you assign a planned order to a production line manually, using the planning table in repetitive manufacturing?  The planned order’s component availability is checked  The planned order’s components are copied from the picking list.  The planned order is converted to a production order.  The planned order generates capacity requirements. NO.43 For a production version to be valid and consistent what requirements must be fulfilled? Note: There are 3 correct answers to this question.  The lot size range must be within the lot-size range of the assigned routing.  The assigned routing must be a rate routing.  Thedeletion flag must NOT be set for the bill of materials (BOM) or the routing.  The assigned routing and bill of materials (BOM) must be valid in the entire validity period.  The assigned routing must NOT have alternative sequences.  Loading … SAP C_TS422_2020 Exam Syllabus Topics: TopicDetailsTopic 1Introduction to SAP S4HANA Supply Chain Planning Identify features for Good Manufacturing Practices (GMP)Topic 2Material Requirements Planning in SAP S4HANA Describe its main components, the lines of business, and the SAP User Experience strategyTopic 3Outline both motivation and background of SAP S4HANA Detailed scheduling planning board) and advanced planningTopic 4Describe the SAP HANA database concept and new user experience with SAP Fiori Explain line load planning and confirmation, outline Kanban master data and Kanban processes   Verified C_TS422_2020 dumps Q&As Latest C_TS422_2020 Download: https://www.testkingfree.com/SAP/C_TS422_2020-practice-exam-dumps.html --------------------------------------------------- Images: https://blog.testkingfree.com/wp-content/plugins/watu/loading.gif https://blog.testkingfree.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2022-09-29 13:28:25 Post date GMT: 2022-09-29 13:28:25 Post modified date: 2022-09-29 13:28:25 Post modified date GMT: 2022-09-29 13:28:25