NEW QUESTION 17
You are the NACE Level 2 Inspector on a project where overcoating of galvanized steel is being performed. The specification references SSPC SP 16 as the surface preparation method. At the pre-job meeting operations personnel make it clear that abrasive blasting will not permitted. The Owner’s representative asks you what other methods might be used.
Of the options shown below, what would be the preferred option in this situation?

 
 
 
 

NEW QUESTION 18
NACE International Standards are developed by:

 
 
 
 

NEW QUESTION 19
WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)

 
 

NEW QUESTION 20
Which type of pipelines collect the gas from the transmission system so utility companies can distribute the gas to end users?

 
 
 
 

NEW QUESTION 21
Coating application to concrete substrates is:

 
 
 
 

NEW QUESTION 22
External coatings applied to buried pipelines are generally tested for:

 
 
 
 

NEW QUESTION 23
You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1 st time you have seen field based centrifugal blast cleaning. You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined in the standard as an acceptable variation in appearance.
Your FIRST preferred course of action is to:

 
 
 
 

NEW QUESTION 24
Steel shot grit contaminated with oil or grease used in a cetrifugal blast cleaning should be

 
 
 
 

NEW QUESTION 25
The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector.
Your FIRST preferred course of action is to:

 
 
 
 

NEW QUESTION 26
NACE/SSPC Water Jetting standards are directly equivalent to ISO Abrasive Blast Standards:

 
 

NEW QUESTION 27
Generally for safety considerations, waterjetting hose connections use

 
 
 
 

NEW QUESTION 28
Thermal Spray coatings provide:

 
 
 
 

NEW QUESTION 29
You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated relative humidity below 40%; however on the second shift of coating application your readings are indicting 80%.
Your FIRST preferred course of action is to:

 
 
 
 

NEW QUESTION 30
You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value.
As this is not part of the standard you should:

 
 
 
 

NEW QUESTION 31
When working with someone who is very concerned about Stability and maintaining adherence to the status-quo, the Inspector should try to:

 
 
 
 

NEW QUESTION 32
The main reason dehumidification is used during coating operations is to

 
 
 
 

NEW QUESTION 33
NACE Level 2 Inspectors have been authorized to perform:

 
 
 
 

NEW QUESTION 34
Inspectors perform tests on linings that they may not perform on exterior coatings because

 
 
 
 

NEW QUESTION 35
When environmental enclosures are being used an inspector needs to be concerned about:

 
 
 
 

NEW QUESTION 36
When observing design defects the NACE Inspector should:

 
 
 
 

Try Free and Start Using Realistic Verified NACE-CIP2-001 Dumps Instantly.: https://www.testkingfree.com/NACE/NACE-CIP2-001-practice-exam-dumps.html

Post date: 2023-01-11 10:09:59
Post date GMT: 2023-01-11 10:09:59
Post modified date: 2023-01-11 10:09:59
Post modified date GMT: 2023-01-11 10:09:59