This page was exported from Testking Free Dumps [ http://blog.testkingfree.com ] Export date:Thu Jan 16 16:21:05 2025 / +0000 GMT ___________________________________________________ Title: Ace NACE NACE-CIP2-001 Certification with Actual Questions Jan 11, 2023 Updated [Q17-Q36] --------------------------------------------------- Ace NACE NACE-CIP2-001 Certification with Actual Questions Jan 11, 2023 Updated 2023 The Most Effective NACE-CIP2-001 with 100 Questions Answers NEW QUESTION 17You are the NACE Level 2 Inspector on a project where overcoating of galvanized steel is being performed. The specification references SSPC SP 16 as the surface preparation method. At the pre-job meeting operations personnel make it clear that abrasive blasting will not permitted. The Owner’s representative asks you what other methods might be used.Of the options shown below, what would be the preferred option in this situation?  SP 1 followed by acid etching  SP 1 followed by caustic etching  SP 1 followed by SP 2  SP 1 followed by SP 3 NEW QUESTION 18NACE International Standards are developed by:  Government mandates  International mandates  Standard committees  Regional mandates NEW QUESTION 19WJ-1 is always performed using UHWJ at pressures above 210 MPa (30,000 PSI)  True  False NEW QUESTION 20Which type of pipelines collect the gas from the transmission system so utility companies can distribute the gas to end users?  Gathering  Midstream  Transmission  Distribution NEW QUESTION 21Coating application to concrete substrates is:  More challenging than coating steel  Less challenging, than coating steel  The same as coating steel  Not required as Concrete is inorganic NEW QUESTION 22External coatings applied to buried pipelines are generally tested for:  Gloss level  Chalking resistance  Cathodic disbondment  Solvent resistance NEW QUESTION 23You are NACE Level 2 Inspector working on a tank lining job where a mobile centrifugal blast unit is being used to blast the tank floor to a NACE No.1/SSPC SP 5. The Contractor has completed his final blast and has called for a hold point inspection. This is the 1 st time you have seen field based centrifugal blast cleaning. You observe what appears to be staining on the substrate however the Contractor assures you this is normal when using centrifugal blast units and what you are seeing is what is defined in the standard as an acceptable variation in appearance.Your FIRST preferred course of action is to:  Request that the Contractor re-blast the floor  Review the standard with the Contractor and re-inspect the floor  Shut the job down  Call your supervisor NEW QUESTION 24Steel shot grit contaminated with oil or grease used in a cetrifugal blast cleaning should be  washed with clean potable water prior to Use.  mixed with uncontaminated abrasive  run through the air wash separator.  disposed of properly. NEW QUESTION 25The coating applicator has ignored a enface preparation hold point and applied coating over the surface without a sign off from you as the inspector.Your FIRST preferred course of action is to:  Stop the job  Require the Applicator to remove the coating  Advise the Owner and write a Non-Conformance report  Ignore the situation NEW QUESTION 26NACE/SSPC Water Jetting standards are directly equivalent to ISO Abrasive Blast Standards:  True  False NEW QUESTION 27Generally for safety considerations, waterjetting hose connections use  an oil/water separator.  a long wand.  a whip-lock device.  filters. NEW QUESTION 28Thermal Spray coatings provide:  Barrier protection  Inhibitive protection  Sacrificial protection  Thermal protection NEW QUESTION 29You are the NACY Coating Inspector on a tank lining project where desiccant dehumidification is being used. Since the first shift of abrasive blasting your readings have indicated relative humidity below 40%; however on the second shift of coating application your readings are indicting 80%.Your FIRST preferred course of action is to:  Check to See if the dehumidification equipment is operating correctly  Call your supervisor  Advise the coating applicator supervisor of your readings  Document the readings at the end of the shift NEW QUESTION 30You are the NACE Level 2 Coating Inspector where SSPC PA 2 has been specified with an additional requirement that no individual gauge reading shall be below a certain value.As this is not part of the standard you should:  Ignore the additional requirement  Enforce the additional requirement  Call your supervisor  Request clarification from the specifier NEW QUESTION 31When working with someone who is very concerned about Stability and maintaining adherence to the status-quo, the Inspector should try to:  Implement immediate to get them motivated  Give them as much advance notice as possible about upcoming changes  Challenge their value to the team and try to get them out of their comfort zone  Make sure they are the center of attention in all site meetings NEW QUESTION 32The main reason dehumidification is used during coating operations is to  control the environment  reduce the possibility of missing the recoat window.  allow the contractor to guarantee the completion date.  avoid repetitive blasting/coating operations. NEW QUESTION 33NACE Level 2 Inspectors have been authorized to perform:  All types of inspection without supervision  Visual inspection and Non-destructive testing  Visual inspection, Non-Destructive and Destructive testing  Visual inspection only NEW QUESTION 34Inspectors perform tests on linings that they may not perform on exterior coatings because  coatings are more durable than linings.  coatings are expected to degrade over time.  linings protect the contents and the container.  linings are more durable than coatings. NEW QUESTION 35When environmental enclosures are being used an inspector needs to be concerned about:  Lighting  Air changes  Structural integrity  a), b), and c) NEW QUESTION 36When observing design defects the NACE Inspector should:  Document the defect and the potential problems that could result  Ignore the defect as the inspector can’t change the design  Request that the item be rebuilt with a better design for coating  Stop the job immediately  Loading … Try Free and Start Using Realistic Verified NACE-CIP2-001 Dumps Instantly.: https://www.testkingfree.com/NACE/NACE-CIP2-001-practice-exam-dumps.html --------------------------------------------------- Images: https://blog.testkingfree.com/wp-content/plugins/watu/loading.gif https://blog.testkingfree.com/wp-content/plugins/watu/loading.gif --------------------------------------------------- --------------------------------------------------- Post date: 2023-01-11 10:09:59 Post date GMT: 2023-01-11 10:09:59 Post modified date: 2023-01-11 10:09:59 Post modified date GMT: 2023-01-11 10:09:59