UPDATED [Oct 21, 2026] Pass PRINCE2 7 Foundation written Exam Exam with Latest Questions [Q276-Q293]

Rate this post

UPDATED [Oct 21, 2026] Pass PRINCE2 7 Foundation written Exam Exam with Latest Questions

PR2F Exam Practice Questions prepared by EXIN Professionals

EXIN PR2F Exam Syllabus Topics:

Section Weight Objectives
Topic 1: People 14% – People in Successful Projects

  • 1. Leadership
  • 2. Stakeholder Engagement
  • 3. Organizational Change Management
  • 4. Communication
Topic 2: PRINCE2 Principles 8% – Applying the Principles

  • 1. Define Roles, Responsibilities and Relationships
  • 2. Ensure Continued Business Justification
  • 3. Manage by Exception
  • 4. Manage by Stages
  • 5. Tailor to Suit the Project
  • 6. Focus on Products
  • 7. Learn from Experience
Topic 3: Key Concepts Relating to Projects and PRINCE2 3% – Project Characteristics

  • 1. PRINCE2 Overview
  • 2. Definition of a Project
  • 3. Project Performance Aspects
Topic 4: PRINCE2 Practices 60% – Project Management Practices

  • 1. Progress
  • 2. Business Case
  • 3. Plans
  • 4. Quality
  • 5. Risk
  • 6. Organizing
  • 7. Issues
Topic 5: PRINCE2 Processes 15% – Project Lifecycle Processes

  • 1. Controlling a Stage
  • 2. Closing a Project
  • 3. Managing Product Delivery
  • 4. Initiating a Project
  • 5. Directing a Project
  • 6. Managing a Stage Boundary
  • 7. Starting Up a Project

 

Q276. As part of the ‘closing a project’ process, the project manager needs to assess whether the outcomes are likely to deliver the expected performance improvements post-project.
In which step of ‘business case management’ technique should the project manager assess this?

 
 
 
 

Q277. The project manager has proposed that a request for change be implemented, but the change authority has asked for more information.
In which step of the ‘issue management technique should the change authority request this information?

 
 
 
 

Q278. Which statement describes the responsibilities of a risk actionee?

 
 
 
 

Q279. Which process is triggered towards the end of the final stage when all the assigned work has been completed?

 
 
 
 

Q280. Which is a benefit of using PRINCE2?

 
 
 
 

Q281. What is a risk actionee responsible for?

 
 
 
 

Q282. Which is NOT considered when defining risk tolerance?

 
 
 
 

Q283. Which level of management uses the mechanisms established by the Progress theme to control any unacceptable deviations?

 
 
 
 

Q284. Identify the missing word(s) in the following sentence.
The ‘controlling a stage’ process is used to manage and control each [ ? ] of a project.

 
 
 
 

Q285. Identify the missing word(s) in the following sentence. The Quality theme provides a set of rules and procedures which ensure that the [ ? ] created meet(s) the needs of the business.

 
 
 
 

Q286. Which describes a risk event?

 
 
 
 

Q287. Which is a purpose of the ‘controlling a stage’ process?

 
 
 
 

Q288. Which aspect of project performance must be managed to ensure the project’s products are fit for purpose?

 
 
 
 

Q289. Which is a purpose of the Starting up a Project process?

 
 
 
 

Q290. Which is a purpose of the Risk theme?

 
 
 
 

Q291. Which is part of quality control?

 
 
 
 

Q292. Which is performed as part of the recommended risk management procedure?

 
 
 
 

Q293. Which is a purpose of the Directing a Project process?

 
 
 
 

PR2F Exam Practice Materials Collection: https://www.testkingfree.com/EXIN/PR2F-practice-exam-dumps.html

         

Related Links: myportal.utt.edu.tt ronorp.net myportal.utt.edu.tt myportal.utt.edu.tt myportal.utt.edu.tt www.stes.tyc.edu.tw

Related Posts

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below