PMI PgMP Exam Syllabus Topics:

Section Weight Objectives
Stakeholder Management 16% – Develop strategies to engage stakeholders effectively throughout the program lifecycle.
– Identify stakeholders and analyze their expectations and interests.
Program Life Cycle Management 44% – Coordinate the concurrent and sequential execution of program components.
– Managing the program from initiation to closure, including planning, execution, and monitoring.
Governance 14% – Establish a governance framework including policies, procedures, and standards.
– Maintain oversight and decision-making frameworks across the program lifecycle.
Strategic Program Management 15% – Define the program mission statement by evaluating the stakeholders’ expectations.
– Establish a high-level road map with milestones and preliminary estimates to obtain initial validation and approval from the executive sponsor.
– Perform an initial program assessment by defining the program objectives, requirements, and risks to ensure alignment with the organization’s strategic plan, objectives, priorities, vision, and mission statement.
– Define the high-level road map and financial framework to set a baseline for program definition, planning, and execution.
Benefits Management 11% – Identify, plan, and manage benefits realization.
– Ensure that the program achieves its intended benefits and value creation.

 

QUESTION 376
Which of the following statements are true regarding the Monitoring and Controlling Program Risks process?
Each correct answer represents a complete solution. Choose all that apply.

 
 
 
 

QUESTION 377
A program manager for a construction program composed of five components is working on the first monthly status report based on preestablished key performance indicators (KPIs). The program sponsor asks the program manager about the contents of the report, which will be sent to program stakeholders. How should the program manager respond?

 
 
 
 

QUESTION 378
Harriet is the program manager of a large program that has a high profile and visibility in her organization.
Some of the stakeholders are negative and Harriet needs to work with these stakeholders to address their fears, perceived threats, and concerns about the program. Which communication method is considered to be the best approach for this scenario?

 
 
 
 

QUESTION 379
You are the program manager for your organization. Management has asked that you determine when resources, such as leased equipment, are no longer needed so that you may release the resources to save time, money, and utilization of resources within your program. What program management process is management asking you to perform?

 
 
 
 

QUESTION 380
You are the project manager for your organization. Your project team has finished the second phase of a seven-phase project. At the end of each phase, management must review the work your project team has completed and determine if the project should be allowed to continue.
What name describes this type of end-of-phase review management is completing on your project?

 
 
 
 

QUESTION 381
The risk manager completes risk response planning. The risk manager believes that to effectively address all eventualities, an additional action is required.
What should the program manager do next?

 
 
 
 

QUESTION 382
Terri is the program manager for her organization and she’s working with Alice, a project manager in her program. Alice calls Terri and insists that she add a change to program scope.
Terri agrees that the change should be entertained. What must Alice do to move forward with her change request?

 
 
 
 

QUESTION 383
You are the program manager for your organization and are coaching Bonnie, a project manager, who would like to be a program manager wants to know what a program is. Which one of the following statements best defines what a program is for Bonnie?

 
 
 
 

QUESTION 384
You are the program manager for your company and evaluating the sellers to determine the seller to buy from. In your analysis you’ve created a histogram to display the pros and cons for each seller. You’ve created five categories of interest and assigned values to each category for each vendor. Your five categories are:
Cost

Schedule

Experience

Certification

Warranty

Each category has a different point value and the vendor that receives the maximum points in total will win the contract. What type of seller evaluation are you performing?

 
 
 
 

QUESTION 385
Recent increments in a software development program have failed testing protocols. The program sponsor is becoming concerned with this pattern because it has resulted in increased costs and delayed schedules. What should the program manager do to prevent this from recurring?

 
 
 
 

QUESTION 386
A program manager has established the policies, procedures, and standards at the beginning of a large-scale software development program and has communicated them to all stakeholders.
However, the program manager notices that some of the agile teams are deviating from the agreed-upon standards and successfully using different tools and techniques for their work. What should the program manager do?

 
 
 
 

QUESTION 387
Mike is the program manager of the NHQ Program. Mike and a vendor are in disagreement over the deliverable the vendor has created for Mike’s program. Mike does not believe the vendor has correctly created the deliverable, while the vendor is adamant that his company has indeed completed the contract. Both parties have documented their stance in the debate. This is an example of what?

 
 
 
 

QUESTION 388
The intermediate benefits of an international e-commerce program decrease incrementally and chronologically during the delivery phase. These decreases are due to currency inflation and increased transportation costs. Which documents should the program manager use to document these changes?

 
 
 
 

QUESTION 389
A software development program will launch iterative versions of new software called Alpha over two years. Following that, a program will be released to the program team and developers to create new software called Beta. While the program manager prepares the program closure plan for Alpha, the program sponsor expresses concern about its support after program closure.
What should the program manager do as part of Alpha’s program closure plan?

 
 
 
 

QUESTION 390
You are the program manager for your organization. Your program has a budget of $750,000 and is expected to last one year. The program is currently 30 percent complete and has spent $245,000. The program is supposed to be 40 percent at this time. What is the cost performance index for this program?

 
 
 
 

QUESTION 391
An R&D group director approves a major program’s charter. Although the director has a high level of understanding of the program’s scope, they are unsure of how the program manager can be successful in delivering the program’s commitments.
What should the program manager do to align stakeholders with planning and monitoring the program’s progress?

 
 
 
 

QUESTION 392
Which of the following directs the improvement efforts to those areas that will have the biggest impact?

 
 
 
 

QUESTION 393
Which of the following risk response planning techniques is associated with threats and seeks to reduce the probability of occurrence, or impact of risk below an acceptable threshold?

 
 
 
 

QUESTION 394
An infrastructure program has 20 projects. The first half of these projects incurred multiple change orders and failed to be completed on time. The program manager meets with the project managers to discuss lessons learned and to understand the challenges. During the meeting, the project managers complain that key risks and a lack of resources resulted in missing deadlines.
What should the program manager do to ensure that the remaining 10 component projects stay on track?

 
 
 
 

QUESTION 395
A program manager is asked to work on a program that has not been set up properly and is not set up to achieve the established program benefits. What should the program manager do?

 
 
 
 

QUESTION 396
You are the program manager for your organization. As your program is being initiated there is some initial concern from the management about the utilization of resources in your program and the need for resources in their day-to-day roles in operations. Management has set a limit on your program that resources may only work 20 hours per week on the program. What is this limit of resource hours in a time period known as?

 
 
 
 

QUESTION 397
A company’s marketing department fails an internal compliance audit. To comply with the auditor’s remediation plan, the legal department mandates that a content management system (CMS) be implemented. After initiating the program for CMS implementation, the program manager discovers that the marketing department has already preselected which CMS technology will be implemented.
What should the program manager do to ensure the success of the program?

 
 
 
 

QUESTION 398
Stakeholders ask the program manager to assess reasons for the project’s delay and provide a report. Also, the program manager must identify steps to be taken to ensure the program will finish on time and within budget.
The program manager distributes information in accordance with which of the following?

 
 
 
 

QUESTION 399
You are the program manager for your organization. You are examining the order of the activities in your program schedule and would like to change some of the ordering to alleviate scheduling conflicts, risks, and based on your experience with the discipline the program uses. Some of the activities you can rearrange while some of the activities must be completed in a particular order. What term describes the activities that must happen in a particular order?

 
 
 
 

Use Real Dumps – 100% Free PgMP Exam Dumps: https://www.testkingfree.com/PMI/PgMP-practice-exam-dumps.html

         

Related Links: www.stes.tyc.edu.tw myportal.utt.edu.tt www.stes.tyc.edu.tw www.stes.tyc.edu.tw myportal.utt.edu.tt www.stes.tyc.edu.tw

Related Posts

Leave a Reply

Your email address will not be published. Required fields are marked *

Enter the text from the image below